Article ID: | iaor19942209 |
Country: | United States |
Volume: | 40 |
Issue: | 2 |
Start Page Number: | 280 |
End Page Number: | 284 |
Publication Date: | Feb 1994 |
Journal: | Management Science |
Authors: | Hung Rudy |
Keywords: | personnel & manpower planning |
Novel workweek arrangements have gained acceptance in many seven-days-a-week operations, such as hospitals and data processing centers. This note considers a multiple-shift workforce scheduling scenario for seven-days-a-week operations under a workweek arrangement called the 3-4 workweek. The present model seeks to minimize the workforce size subject to satisfying staffing requirements and workrules relating to off-days, off-weekends, and work-stretches. The paper provides an efficient optimal algorithm which is intuitive and simple enough to be implemented by hand.