Article ID: | iaor19932044 |
Country: | United Kingdom |
Volume: | 44 |
Issue: | 1 |
Start Page Number: | 71 |
End Page Number: | 80 |
Publication Date: | Jan 1993 |
Journal: | Journal of the Operational Research Society |
Authors: | Willis R.J., Li R., K.-Y. |
Keywords: | project management |
This paper presents a practical approach for resource constrained scheduling within a given project duration. The method ensures a stable project plan when activity durations are reduced to achieve this. It handles all four categories of resource (unconstrained, renewable, non-renewable and doubly-constrained resources), and aims to shorten the project duration at minimum cost. Soft constraints and resource availabilities which vary over time are allowed in the method. Computational experience is reported.