Article ID: | iaor201527185 |
Volume: | 234 |
Issue: | 3 |
Start Page Number: | 751 |
End Page Number: | 762 |
Publication Date: | May 2014 |
Journal: | European Journal of Operational Research |
Authors: | Guan Yongpei, Zhang Muhong, Jiang Ruiwei, Li Guang |
Keywords: | quality & reliability, heuristics, networks, allocation: resources |
For a current deregulated power system, a large amount of operating reserve is often required to maintain the reliability of the power system using traditional approaches. In this paper, we propose a two‐stage robust optimization model to address the network constrained unit commitment problem under uncertainty. In our approach, uncertain problem parameters are assumed to be within a given uncertainty set. We study cases with and without transmission capacity and ramp‐rate limits (The latter case was described in Zhang and Guan (2009), for which the analysis part is included in Section 3 in this paper). We also analyze solution schemes to solve each problem that include an exact solution approach and an efficient heuristic approach that provides tight lower and upper bounds for the general network constrained robust unit commitment problem. The final computational experiments on an IEEE 118‐bus system verify the effectiveness of our approaches, as compared to the nominal model without considering the uncertainty.