Article ID: | iaor20115089 |
Volume: | 23 |
Issue: | 2 |
Start Page Number: | 189 |
End Page Number: | 204 |
Publication Date: | Mar 2011 |
Journal: | INFORMS Journal on Computing |
Authors: | Megow Nicole, Mhring Rolf H, Schulz Jens |
Keywords: | scheduling, risk, heuristics, programming: integer |
Large‐scale maintenance in industrial plants requires the entire shutdown of production units for disassembly, comprehensive inspection, and renewal. We derive models and algorithms for this so‐called turnaround scheduling that include different features such as time‐cost trade‐off, precedence constraints, external resource units, resource leveling, different working shifts, and risk analysis. We propose a framework for decision support that consists of two phases. The first phase supports the manager in finding a good makespan for the turnaround. It computes an approximate project time‐cost trade‐off curve together with a stochastic evaluation. Our risk measures are the expected tardiness at time