Materials requirement planning (MRP) systems have several lot-sizing rules, of which the periodic order quantity rule is the most widely used in practice. With this rule groups of items are ordered on a common order cycle or frequency. This article presents empirical evidence to show that when the order cycles are set in a geometric progression then they are indeed optimum.