Minimizing makespan on a two-machine re-entrant flowshop

Minimizing makespan on a two-machine re-entrant flowshop

0.00 Avg rating0 Votes
Article ID: iaor20082427
Country: United Kingdom
Volume: 58
Issue: 7
Start Page Number: 972
End Page Number: 981
Publication Date: Jul 2007
Journal: Journal of the Operational Research Society
Authors: ,
Keywords: heuristics, programming: branch and bound
Abstract:

This paper focuses on a two-machine re-entrant flowshop scheduling problem with the objective of minimizing makespan. In the re-entrant flowshop considered here, all jobs must be processed twice on each machine, that is, each job should be processed on machine 1, machine 2 and then machine 1 and machine 2. We develop dominance properties, lower bounds and heuristic algorithms for the problem, and use these to develop a branch and bound algorithm. For evaluation of the performance of the algorithms, computational experiments are performed on randomly generated test problems. Results of the experiments show that the suggested branch and bound algorithm can solve problems with up to 200 jobs in a reasonable amount of CPU time.

Reviews

Required fields are marked *. Your email address will not be published.