| Article ID: | iaor20081726 |
| Country: | United Kingdom |
| Volume: | 10 |
| Issue: | 1 |
| Start Page Number: | 67 |
| End Page Number: | 76 |
| Publication Date: | Feb 2007 |
| Journal: | Journal of Scheduling |
| Authors: | Laguna Manuel, Armentano Vincius Amaral, Yamashita Denise Sato |
| Keywords: | project management, heuristics, heuristics: tabu search |
We address a project scheduling problem with resource availability cost for which the activity durations are uncertain. The problem is formulated within the robust optimization framework, where uncertainty is modeled via a set of scenarios. The proposed solution method is based on the scatter search methodology and employs advanced strategies, such as dynamic updating of the reference set, a frequency-based memory mechanism, and path relinking. A multistart heuristic was also developed and comparative results are reported. The tradeoffs for risk-averse decision makers are discussed.