Article ID: | iaor20062068 |
Country: | United Kingdom |
Volume: | 44 |
Issue: | 4 |
Start Page Number: | 715 |
End Page Number: | 728 |
Publication Date: | Jan 2006 |
Journal: | International Journal of Production Research |
Authors: | Choi B.-C., Yoon S.-H., Chung S.J. |
In this paper, we consider the problem of minimizing the total weighted completion time in an n-job, two-machine proportionate flow shop, where job processing times are inversely proportional to machine speeds. We show that the problem is NP-complete. We provide a tight lower bound to an optimal objective value and show that the worst-case performance ratio of the weighted shortest processing time rule is less than 2. We propose heuristic procedures to find an approximate solution for the problem. A computational study on randomly generated test problems is conducted to investigate the performance of the proposed heuristics.