Article ID: | iaor1991185 |
Country: | United Kingdom |
Volume: | 28 |
Issue: | 8 |
Start Page Number: | 1459 |
End Page Number: | 1470 |
Publication Date: | Aug 1990 |
Journal: | International Journal of Production Research |
Authors: | Akella A., Maimon O., Gershwin B. |
Keywords: | programming: linear |
In this paper, the authors develop a linear programming framework for computing a quadratic approximation to the value function, which constitutes the off-line computation of a hierarchical FMS scheduling approach previously developed by us. In contrast to previous work, where relatively crude value functions were used, they develop a quadratic approximation that is a prior fit. The authors consider the multiple part multiple machine discounted cost case and illustrate the approach via a simulation example in the context of an industrial setting.