                                                                                | Article ID: | iaor1990526 | 
| Country: | United States | 
| Volume: | 36 | 
| Issue: | 3 | 
| Start Page Number: | 1 | 
| End Page Number: | 7 | 
| Publication Date: | Mar 1990 | 
| Journal: | Management Science | 
| Authors: | Carreno Jose Juan . | 
This paper deals with an identical multiprocessor, multiproduct, lot-size scheduling problem under deterministic conditions. The problem is an extension of the single-processor ELSP problem. The objective is to minimize the average production and inventory costs per unit time subject to constraints of no shortages and no interference among the products. A mathematical formulation for the problem is given. A heuristic procedure, which extends the Common Cycle approach for a single processor, is suggested and computational results are reported. Upper and Lower bounds are developed and used to measure the effectiveness of the procedure.