| Article ID: | iaor19992198 |
| Country: | United Kingdom |
| Volume: | 49 |
| Issue: | 11 |
| Start Page Number: | 1196 |
| End Page Number: | 1205 |
| Publication Date: | Nov 1998 |
| Journal: | Journal of the Operational Research Society |
| Authors: | Drexl Andreas, Kimms A. |
| Keywords: | production, scheduling |
This paper deals with proportional lot sizing and scheduling (PLSP) and gives some insights into the properties of this problem. Such insights may be useful for developing heuristic and/or exact solution procedures. The emphasis of this paper is on the multi-level, multi-machine case. We provide a mixed-integer programming model, relate it to other models that can be found in the literature, and discuss characteristics which make solving instances of the PLSP-model a hard task.