A very fast production scheduler

A very fast production scheduler

0.00 Avg rating0 Votes
Article ID: iaor1995954
Country: United Kingdom
Volume: 14
Start Page Number: 88
End Page Number: 101
Publication Date: Dec 1994
Journal: International Journal of Operations & Production Management
Authors: , ,
Keywords: production
Abstract:

A fast production scheduling system, the very fast scheduler, has been developed by the authors. It creates a capacity constrained production schedule within one minute of elapsed time for problems of a size encountered in industry. The quality of the schedules is comparable with the best alternative heuristic scheduling techniques. The speed of the scheduler is such that it can be used on a real-time basis to plan capacity, adjust priorities and other parameters and derive new schedules.