An extended model for the joint overhaul scheduling problem

An extended model for the joint overhaul scheduling problem

0.00 Avg rating0 Votes
Article ID: iaor1995461
Country: United Kingdom
Volume: 14
Start Page Number: 37
End Page Number: 43
Publication Date: Oct 1994
Journal: International Journal of Operations & Production Management
Authors: ,
Keywords: scheduling
Abstract:

Deals with planning the maintenance scheduling of a group of non-identical production units. Develops a realistic model for the joint overhaul problem by incorporating the cost of co-ordination. The model selects overhaul schedules that minimize the average total cost of operation which consist of the cost of repairs, the cost of production, and the cost of co-ordination. Proposes a new procedure for solving the problem. Lower costs are obtained for two examples from the literature which were solved using the proposed model.

Reviews

Required fields are marked *. Your email address will not be published.