Time-uncertainty analysis in project networks with a new merge-event time-estimation technique

Time-uncertainty analysis in project networks with a new merge-event time-estimation technique

0.00 Avg rating0 Votes
Article ID: iaor1994569
Country: United Kingdom
Volume: 11
Issue: 3
Start Page Number: 165
End Page Number: 174
Publication Date: Aug 1993
Journal: International Journal of Project Management
Authors: ,
Abstract:

A new analytical merge-event time-estimation technique, called the back-forward uncertainty-esimation procedure, is introduced in the paper to include the time uncertainties of noncritical path activities in the risk analysis of a project network. The BFUE procedure is consistent with the