In this paper, we study the impact of demand uncertainty on the build‐operate‐transfer (BOT) contract design by optimizing a bi‐objective problem via three critical decisions: toll, capacity and concession period. We derive the optimums and identify the public and private sector’s economic incentives. We find that the optimal length of concession period and the service quality of the infrastructure depend on the two parties’ operational costs and negotiation powers. Under mild conditions, we prove that the government will build a larger capacity but charge less than the private sector. Furthermore, the efficiency of BOT contract is improved with demand uncertainty.