Article ID: | iaor20105560 |
Volume: | 21 |
Issue: | 3 |
Start Page Number: | 339 |
End Page Number: | 342 |
Publication Date: | Apr 2010 |
Journal: | Production Planning & Control |
Authors: | Myung Young-Soo |
Keywords: | production, scheduling |
Lee et al. (2004) have introduced a slab caster scheduling problem and developed an optimal algorithm. Their algorithm is efficient but an offline algorithm that we need the information on all the customer orders a priori to implement. In this article, we propose an online algorithm that we can implement without knowledge of the orders yet to arrive. We show that the offline version of our new algorithm also provides an optimal solution and the online version has the worst case performance ratio of 3. We also give a short proof on the correctness of Lee