Lot sizing in reverse MRP for scheduling disassembly

Lot sizing in reverse MRP for scheduling disassembly

0.00 Avg rating0 Votes
Article ID: iaor2009212
Country: Netherlands
Volume: 111
Issue: 2
Start Page Number: 741
End Page Number: 751
Publication Date: Jan 2008
Journal: International Journal of Production Economics
Authors: , ,
Keywords: reverse logistics, lot sizing
Abstract:

Gupta and Taleb presented an algorithm for reverse MRP that can be applied to a product structure in which there is a certain demand for components and a need to know the number of products to disassemble in order to fulfil the demand for those components. However, that algorithm did not consider lot sizing at all. Incorporating lot sizing makes the problem a great deal more challenging in disassembly situations because of the disparity between the number of components present in the product and the demand of the components.