Article ID: | iaor20073644 |
Country: | Greece |
Volume: | 6 |
Issue: | 3 |
Publication Date: | Sep 2006 |
Journal: | Operational Research - An International Journal |
Authors: | Pantouvakis John-Paris, Manoliadis Oddysseus G. |
Keywords: | project management |
In this paper a solution approach is discussed for managing projects with resource constraints. For this purpose a heuristic method is developed based on traditional CPM scheduling calculations and leveling algorithms. The method can be applied using normal scheduling software such as P3 and MS project, and as such, it is of value to practitioners. An illustrative example is also presented herein to exemplify the concepts. The problem solved has importance and direct application to the management of a wide variety of project-structured efforts with prevailing resource constraints.