Article ID: | iaor20063287 |
Country: | China |
Volume: | 23 |
Issue: | 2 |
Start Page Number: | 14 |
End Page Number: | 18 |
Publication Date: | Feb 2005 |
Journal: | Systems Engineering |
Authors: | Xu Yu, He Zhengwen, Chai Guorong, Zhang Jingwen |
Keywords: | scheduling |
To overcome the defects of the current state of research into the project scheduling problem (PSP), the authors put forward a multi-mode flexible resource-constrained PSP with discounted cash flow (MMFRCPSP-DCF). Using flexible resources would not only optimize traditional MMRCPSP, but also provide a bill of resources that should be hired or bought under a fixed activity mode package. The authors analyze the flexible cost, the cost to finish the events, the payments, and the bonus/penalty, and formulate nonlinear integer programming model of MMFRCPSP-DCF. Ultimately, the outcomes of the paper are illustrated by an instance.