Hybrid algorithm for scheduling with regard for reinvestment of profits

Hybrid algorithm for scheduling with regard for reinvestment of profits

0.00 Avg rating0 Votes
Article ID: iaor20042967
Country: Netherlands
Volume: 65
Issue: 3
Start Page Number: 449
End Page Number: 455
Publication Date: Mar 2004
Journal: Automation and Remote Control
Authors: ,
Keywords: scheduling
Abstract:

Scheduling of the interrelated jobs of an investment project was considered. The project can be partially financed from the means obtained by executing its jobs. The net profit value was used as the optimization criterion. The problem is NP-hard. A new hybrid algorithm based on a combination of the branch-and-bound and dynamic algorithms was proposed to determine its optimal solution.