This paper discusses a new approach to job-shop production scheduling with time constraints on starting and completing work. In this approach, all operations in the queue are sorted according to their values of remaining operating time, and a preliminary feasible solution for production scheduling is found, which makes a minimum circulation time of parts in the system. Then adjustment is made to the time span of the block of operations. The process is iterated until a satisfactory scheduling solution is obtained.