Article ID: | iaor20023580 |
Country: | China |
Volume: | 27 |
Issue: | 3 |
Start Page Number: | 387 |
End Page Number: | 391 |
Publication Date: | May 2001 |
Journal: | Acta Automatica Sinica |
Authors: | Mao Ning, Chen Qingxin, Chen Xin |
Keywords: | project management |
This paper deals with the multi-mode multiple resource-constrained project scheduling problem, which is abstracted from modeling the formation process of virtual enterprises of agile manufacturing in the next century. Different from the problem already investigated by other researchers, the problem handled in this paper is of variable resource requirement and renewable resource availability constraints. As an extension to the famous DH-procedure, the branch-and-bound algorithm in this paper can solve this kind of most general project scheduling problems with optimality.