The programmed method of drawing an optimal activity-on-arc network diagram according to the schedule of ordinary precedence activities

The programmed method of drawing an optimal activity-on-arc network diagram according to the schedule of ordinary precedence activities

0.00 Avg rating0 Votes
Article ID: iaor20023435
Country: China
Volume: 21
Issue: 3
Start Page Number: 38
End Page Number: 43
Publication Date: Mar 2001
Journal: Systems Engineering Theory & Practice
Authors: ,
Abstract:

In this paper, we propose a programmed method to draw an optimal activity-on-arrow network diagram according to the schedule of ordinary precedence activities and give an example to illustrate the application of this method.