Article ID: | iaor20022414 |
Country: | Netherlands |
Volume: | 74 |
Issue: | 1/3 |
Start Page Number: | 93 |
End Page Number: | 101 |
Publication Date: | Jan 2001 |
Journal: | International Journal of Production Economics |
Authors: | Dhaenens-Flipo Clarisse |
Keywords: | scheduling |
An aluminium can production problem is considered and restated as a problem of scheduling unrelated parallel machines with sequence-dependent changeover times. The objective is to find the minimal cost schedule that respects a given production horizon. As this time constraint can be very difficult to meet, a bicriterion procedure is proposed to deal with the respect of the production horizon and the minimization of the set of costs (production, distribution, switchings).