| Article ID: | iaor20022414 |
| Country: | Netherlands |
| Volume: | 74 |
| Issue: | 1/3 |
| Start Page Number: | 93 |
| End Page Number: | 101 |
| Publication Date: | Jan 2001 |
| Journal: | International Journal of Production Economics |
| Authors: | Dhaenens-Flipo Clarisse |
| Keywords: | scheduling |
An aluminium can production problem is considered and restated as a problem of scheduling unrelated parallel machines with sequence-dependent changeover times. The objective is to find the minimal cost schedule that respects a given production horizon. As this time constraint can be very difficult to meet, a bicriterion procedure is proposed to deal with the respect of the production horizon and the minimization of the set of costs (production, distribution, switchings).