| Article ID: | iaor20011778 |
| Country: | Netherlands |
| Volume: | 125 |
| Issue: | 3 |
| Start Page Number: | 535 |
| End Page Number: | 550 |
| Publication Date: | Sep 2000 |
| Journal: | European Journal of Operational Research |
| Authors: | Grabowski Jozef, Pempera Jaroslaw |
| Keywords: | heuristics, construction & architecture |
We consider a real-life problem of scheduling clients' orders in the production of concrete blocks in a building industry factory. This problem can be modelled as a hybrid flow shop scheduling problem with mixed no-wait/no-store constraints and mixed bottleneck/non-bottleneck machines. The objective function is to minimize maximum completion time. To solve the problem, we propose an approximation algorithm based on the tabu search approach.