Article ID: | iaor2001221 |
Country: | Netherlands |
Volume: | 64 |
Start Page Number: | 127 |
End Page Number: | 141 |
Publication Date: | Jan 2000 |
Journal: | International Journal of Production Economics |
Authors: | Kolisch R. |
Keywords: | programming: integer |
The problem of scheduling multiple, large-scale, make-to-order assemblies is considered. Beside ‘classical’ precedence and resource constraints as known from resource-constrained project scheduling we take spatial resource and part availability constraints into account. The objective is to minimize the sum of the weighted tardiness. We propose a mixed integer programming model of the problem which is a generalization of three allocation problems. Since the problem is