Article ID: | iaor20003437 |
Country: | Netherlands |
Volume: | 60/61 |
Start Page Number: | 523 |
End Page Number: | 528 |
Publication Date: | Jan 1999 |
Journal: | International Journal of Production Economics |
Authors: | Yura Kenji |
A scheduling method is elucidated for the re-entrant manufacturing systems, where the process route of a job passes production facilities one or more times. The objectives of the scheduling problem are maximization of the production rate as a primary one and minimization of the throughput time as a secondary one. The method makes the cyclic schedule, where an adequate number of jobs are treated as a lot and the lot is cyclically released into the system. The lot size is determined to maximize the production rate, and a sequencing method of the lots is developed to minimize the throughput time.