Article ID: | iaor2000838 |
Country: | United States |
Volume: | 7 |
Issue: | 4 |
Start Page Number: | 387 |
End Page Number: | 401 |
Publication Date: | Dec 1998 |
Journal: | Production and Operations Management |
Authors: | Yan Houmin, Cheng Feng, Yang Jun |
The problem of production planning and setup scheduling of multiple products on a single facility is studied in this paper. The facility can only produce one product at a time. A setup is required when the production switches from one type of product to another. Both setup times and setup costs are considered. The objective is to determine the setup schedule and production rate for each product that minimize the average total costs, which include the inventory, backlog, and setup costs. Under the assumption of a constant production rate, we obtain the optimal cyclic rotation schedule for the multiple products system. Besides the decision variables studied in the classical economic lot scheduling problem (