The problem of planning instablity caused by new and actualized data in material coordination systems with periodic review and replanning activities has been discussed from several viewpoints in literature and it is of great practical importance. The application of a rolling horizon planning framework in forecast-dependent inventory control leads to nervousness in the planning system caused by different order release decisions in successive planning cycles. In this paper a setup-oriented planning stability concerning deviations of planned orders in all periods of a given stability horizon in a single-stage inventory system with arbitrary stochastic demand is analyzed. The influence of an (