Article ID: | iaor1998140 |
Country: | Netherlands |
Volume: | 75 |
Issue: | 2 |
Start Page Number: | 296 |
End Page Number: | 311 |
Publication Date: | Jun 1994 |
Journal: | European Journal of Operational Research |
Authors: | Tempelmeier Horst, Helber Stefan |
Keywords: | production: MRP |
This paper presents an heuristic for the multi-item, multi-level dynamic lotsizing problem in general non-cyclic product/operation structures under multiple capacity constraints. The proposed procedure uses a modification of the Dixon–Silver heuristic to solve a sequence of single-level capacitated multi-item lotsizing problems (CLSP). Within the frame of this general procedure two costing methods and two ways of ordering the product/operation structure are considered. The heuristic is tested on a set of problems for which the optimal solution is available.