A project activity scheduling problem with net present value measure

A project activity scheduling problem with net present value measure

0.00 Avg rating0 Votes
Article ID: iaor19951297
Country: Netherlands
Volume: 37
Issue: 2/3
Start Page Number: 177
End Page Number: 187
Publication Date: Dec 1994
Journal: International Journal of Production Economics
Authors: ,
Abstract:

This paper considers an activity scheduling problem for a project where cash inflows and outflows are given and availability restrictions are imposed on capital and renewable resources. The objective of the problem is to maximize the net present value of the project. Resource-duration interactions are considered in analyzing the problem. A two-phase heuristic solution algorithm is exploited and tested with various numerical problems for its effectiveness and efficiency.