Article ID: | iaor19942185 |
Country: | Netherlands |
Volume: | 6 |
Issue: | 1 |
Start Page Number: | 55 |
End Page Number: | 67 |
Publication Date: | Jan 1994 |
Journal: | International Journal of Flexible Manufacturing Systems |
Authors: | Tetzlaff Ulrich A.W. |
The capacity of a flexible manufacturing system is optimized with the objective to maximize the system’s throughput, while a budget constraint is considered. Decisions are performed on the capacity of machine groups (sets of identical machines), the transportation system and, in case of a significant cost impact, the number of pallets in the system. Throughput evaluation is achieved either by an open finite queueing network or by a closed queueing network if the number of pallets is included in the decision process. For both cases the solution procedure is based on the marginal allocation scheme.