Single‐machine scheduling and slack due‐date assignment with aging effect and deteriorating maintenance
2012
We consider single‐machine scheduling and slack due‐date assignment...
Unrelated parallel‐machine scheduling with aging effects and multi‐maintenance activities
2012
Machine maintenance is often performed in manufacturing to prevent premature machine...
Some unrelated parallel machine scheduling problems with past‐sequence‐dependent setup time and learning effects
2011
In this paper, we study an unrelated parallel machine scheduling problem with setup...
Single‐machine scheduling with deteriorating jobs and setup times to minimize the maximum tardiness
2011
In many realistic production situations, a job processed later consumes more time than...
Unrelated parallel‐machine scheduling with deteriorating maintenance activities
2011
We study the problem of unrelated parallel‐machine scheduling with...
Two due date assignment problems with position‐dependent processing time on a single‐machine
2011
The focus of this study is to analyze single‐machine scheduling and due date...
A single-machine scheduling problem with maintenance activities to minimize makespan
2010
We study a single-machine scheduling problem with periodic maintenance activity under...
A two-stage hybrid flowshop scheduling problem with a function constraint and unrelated alternative machines
2008
This article addresses a two-stage hybrid flowshop scheduling problem with unrelated...
A two-machine flowshop scheduling problem with a separated maintenance constraint
2008
This paper considers a two-machine flowshop scheduling problem with a separated...